Finnish regulatory authority halts Google data center construction over massive forest clear-cutting

Marijan Hassan - Tech Journalist
Oct 29
2 min read

The Finnish Licensing and Supervision Authority (LVV) has ordered Google to immediately halt all key construction and land-alteration activities at two major AI data center development sites in Finland. The regulatory stop-work order was issued after investigations revealed that Google's local subsidiary, Tuike Finland Oy, clear-cut an estimated 400,000 trees across roughly 530 hectares (1,300 acres) of forest before required Environmental Impact Assessments (EIA) were completed.



The enforcement action suspends preparatory work across sites in Muhos and Otanmäki, dealing a regulatory setback to Google’s planned €13 billion ($15 billion) Nordic digital infrastructure expansion.


Extensive Clear-Cutting and Environmental Violations

The environmental controversy centers on the scale of land preparation carried out prior to formal regulatory approval. In Muhos, roughly 330 hectares of forest were cleared, resulting in the removal of approximately 250,000 trees, while another 200 hectares were felled at the Otanmäki site, removing an estimated 150,000 trees.


Key regulatory findings and environmental impacts cited by local authorities and ecological organizations include:

  • Bypassing Mandatory Reviews: Finnish law mandates that large-scale industrial projects undergo comprehensive Environmental Impact Assessments before executing work that significantly alters topsoil or local hydrology. Google cleared topsoil, constructed access roads, and installed drainage networks prior to the completion of these evaluations.

  • Hydrological and Habitat Disruption: Local conservation groups, including the Finnish Association for Nature Conservation (SLL), documented heavy runoff carrying sediment into local waterways feeding the Oulujoki River, alongside severe habitat displacement for local wildlife.


The LVV directive strictly prohibits further tree removal, excavation, topsoil stripping, road construction, and site drainage. Only non-invasive activities, such as land surveying, planning, and soil sampling, are permitted to continue while the EIA process is conducted.


Local Backlash and Corporate Response

The scale of the deforestation sparked public outcry across Finland, drawing criticism from environmental advocates, local residents, and political leaders over the rapid expansion of energy- and land-intensive data infrastructure. Critics noted that while municipalities offered land to attract tech investment, the swift clear-cutting breached long-standing regulatory expectations and public trust.


In response to the regulatory intervention and media scrutiny, Google released a statement reiterating its commitment to compliance and regional restoration. The company stated that it will fully comply with all LVV directives and work actively with Finnish authorities to complete the necessary environmental reviews.


Proposed Remediation

To offset the environmental impact, Google proposed biodiversity mitigation measures, including replanting trees across approximately 130 hectares surrounding the Muhos site.


The halt in Finland highlights growing international friction between technology companies racing to build out mega-scale AI data center capacity and local environmental regulations.